Rockhampton Northern Access Upgrade
The Rockhampton Northern Access Upgrade enhanced capacity, safety and connectivity along one of the region's most important transport corridors, supporting the continued growth of surrounding residential, commercial and industrial areas.
Delivered in joint venture, the project involved duplicating 5.4 kilometres of the Bruce Highway between Yeppoon Road and north of Terranova Drive. The works responded to increasing traffic demands from the rapidly growing Parkhurst and Glenlee communities and included extensive utility relocations, major drainage infrastructure and improved active transport connections. Delivered within a live traffic environment, the upgrade improved network efficiency, strengthened corridor resilience and provided safer, more reliable connections for motorists, cyclists and pedestrians.
-
Sector
Transport, Utilities
-
Client
Department of Transport and Main Roads
-
Location
Bruce Highway, Parkhurst
-
Duration
November 2018 - September 2021
-
Value
$158M
Project Scope
- Duplication of 5.4 km of the Bruce Highway to four lanes
- Realignment of 1.1 km of Boundary Road South
- Construction of 1.6km for two new service roads
- Construction of three new signalised intersections and a dual-lane roundabout at Sterling Drive
Bridgeworks
- Two new bridges over Limestone Creek with PSC piles
- Two new bridges over Ramsey Creek with CIP piles
- Demolition of existing Ramsey Creek and Limestone Creek bridges
- Construction of stormwater and cross-drainage systems
- Installation of 400 m of noise fencing
- Pavement works, road surfacing, and lighting
- Guardrail installation
- Public utility and service relocations including water, gas, electricity, telecom
- Provisions for cyclists and pedestrian traffic