The Cunninghams Gap Reconstruction Project is restoring a critical section of the Cunningham Highway damaged during the 2019 bushfires, improving network resilience and ensuring the continued safe movement of freight, tourists and local communities through this important regional corridor.

Located within Main Range National Park, part of the Gondwana Rainforests World Heritage Area, the project was delivered in a highly constrained environment characterised by steep terrain, challenging geotechnical conditions and significant environmental sensitivities. Constructed in two stages, the works include upslope stabilisation through rockfall protection systems and soil nail retaining structures, as well as downslope improvements involving highway widening, construction of a new western carpark, stabilisation of fractured rock faces and upgrades to existing retaining structures. To overcome the challenges of working within steep, inaccessible terrain, the project utilised tower cranes to safely transport materials and equipment, reducing environmental disturbance, ensuring safety and minimising impacts to road users. Careful staging enabled the highway to remain operational throughout construction, maintaining a vital trade and tourism link while delivering long-term safety, reliability and capacity improvements.

  • Sector

    Natural disaster recovery, Slope stabilisation, Transport, Utilities

  • Client

    Department of Transport and Main Roads

  • Location

    Cunningham Highway, Tregony, QLD

  • Duration

    October 2022 - July 2026

  • Value

    The Queensland Reconstruction Authority (QRA) formally confirms and reconciles the final project value during the project close-out and financial acquittal process once the DRFA project has been completed.

Project Scope

Stage 1 – Upslope Stabilisation

  • Installed rockfall and slope protection systems
  • Constructed soil nail retaining structures

Stage 2 – Downslope Stabilisation and Widening

  • Designed and constructed western carpark
  • Installed soil nails in fractured rock
  • Geotechnical improvements to existing downslope retaining structures

Overall Works

  • Slope scaling and stabilisation
  • Rockfall protection systems
  • Retaining structures
  • Replaced existing concrete barriers
  • Replaced existing guardrail and installation of motorcycle protection guardrail
  • Wide centre line treatments
  • Replaced of existing chain wire fencing

Overall Works

  • Drainage works
  • Slope monitoring technology
  • Solar road lighting
  • Pavement works
  • Soil nailing and micropiling
  • Passive rock dowel installation