Lamington National Park Road NDRRA

McIlwain restored and stabilised multiple landslip sites along Lamington National Park Road following ex-Tropical Cyclone Debbie, delivering critical infrastructure repairs that improved network resilience and maintained a vital connection for residents, tourists and local businesses.

Following widespread geotechnical failures, the Department of Transport and Main Roads engaged McIlwain to deliver remediation works across a highly constrained and environmentally sensitive corridor. The project initially comprised 32 civil works sites and more than 50 rock scaling, clearing and revegetation locations, later expanding to include a further 28 sites through design and construct variations. Working collaboratively with GHD and PCA, McIlwain developed and implemented innovative stabilisation solutions, including micropiled A-Frame structures, hollow bar soil nails and Geobrugg mesh systems, tailored to the unique conditions of each site. Despite the significant increase in scope, the project was completed on time and under budget, earning the 2019 CCF Earth Award for Excellence in Civil Construction ($10M–$30M).

  • Sector

    Natural disaster recovery, Slope stabilisation, Transport

  • Client

    Department of Transport and Main Roads

  • Location

    Lamington National Park Road, Sarabah, QLD

  • Duration

    December 2017 - December 2019

  • Value

    $26.6M

  • Award

    2019 CCF Earth Award for Excellence in Civil Construction ($10M–$30M).

Project Scope

  • 11,700m² hand scaling off ropes
  • 270m³ shotcreting batters off ropes
  • 1,300m soil nails off ropes and 4,600m with excavator
  • Installation of 600m micropiles, 115 steel columns, 1,100 concrete sleepers
  • Installation of 244m bored and reinforced concrete piles, 120m capping beam
  • Construction of 1,011m³ reinforced concrete retaining wall footing
  • Installation of 2,700m³ gabions, pre-filled and craned into place
  • 7,000m² clearing and grubbing
  • 1,200m concrete kerb, 1,200m³ lightly bound pavement
  • 20,500 litres of seal
  • 6,000m² revegetation