Project details

Contract value

$7,400,000

Client

Department of Transport & Main Roads

Duration

Nov 2015 - Aug 2016

Project description

  • Culvert construction
  • Pavement drainage
  • Subsoil drainage
  • 33,000m2 Clearing and grubbing
  • 13,580m3 road excavation
  • 5,895m3 stabilisation with plant mixed foamed bitumen
  • Mill existing material and dispose – 18,920m2
  • Sprayed bituminous surface – 58,500 litre
  • Removal and storage road furniture
  • Signage
  • Guardrails
  • Linemarking
  • Landscaping and stockpile remediation

This $7.4M contract has delivered several safety improvements for motorist along the D’Aguilar Highway between Station Road and Gamgee Road. The project included; a new intersection and dedicated turning lanes, lighting solutions, drainage improvements, construction of a 1.2km eastbound overtaking lane and resealing surfaces between Neurum Road and Canado Street.

Pavement designs for this contract required the use of plant mixed foam bitumen which is a new technology adopted by DTMR. This new technique delivers a fast, cost-effective and long-term rehabilitation solution that reduces road maintenance.

McIlwain collaborated with DTMR where changes were made to the specifications to create a sustainable solution. Learning from this project will be used to develop further the foam bitumen specification which contractors will see in future rehabilitation contracts.

The construction team handed the project over to DTMR two weeks ahead of schedule and works were completed on budget.