Mount Victoria Slope Remediation

McIlwain delivered permanent slope stabilisation works on the eastbound carriageway near Fairy Bower Road at Mount Victoria, strengthening the long-term resilience of this critical transport corridor and ensuring continued safe access for road users.

Following significant rainfall in March 2022, cracking and a shallow slope failure developed above the rail bridge at Mount Victoria, requiring a permanent remediation solution to address ongoing geotechnical and operational risks. Engaged by Transport for NSW, McIlwain delivered the works within a constrained live transport environment, requiring meticulous planning, staged construction and close stakeholder coordination. The project was carefully programmed to maintain safety, minimise disruption to road users and deliver a more resilient, long-term outcome for the local community. Environmental rehabilitation formed an important component of the works, with more than 150 trees planted and site-generated mulch reused to support revegetation, stabilise disturbed areas and enhance the surrounding landscape.

  • Sector

    Natural disaster recovery, Slope stabilisation, Transport

  • Client

    Transport for NSW

  • Location

    Mount Victoria, NSW

  • Duration

    January 2025 - October 2025

  • Value

    $20M

Project Scope

  • Establishment of a temporary work site to enable safe construction access
  • Strengthening of an existing track behind the slope for access and operations
  • Clearing and trimming of vegetation
  • Installation of 2,600 lm of soil nails
  • Application of 900 m² of shotcrete with mock rock finish
  • Installation of horizontal drainage across the slope
  • Construction of 110 lm of rockfall fencing
  • Installation of 226 lm of guardrail
  • Replacement of road shoulder pavement

  • Construction of 33 lm of concrete drainage with mock rock finish
  • Site restoration including revegetation and landscaping