Mount Victoria Slope Remediation
McIlwain delivered permanent slope stabilisation works on the eastbound carriageway near Fairy Bower Road at Mount Victoria, strengthening the long-term resilience of this critical transport corridor and ensuring continued safe access for road users.
Following significant rainfall in March 2022, cracking and a shallow slope failure developed above the rail bridge at Mount Victoria, requiring a permanent remediation solution to address ongoing geotechnical and operational risks. Engaged by Transport for NSW, McIlwain delivered the works within a constrained live transport environment, requiring meticulous planning, staged construction and close stakeholder coordination. The project was carefully programmed to maintain safety, minimise disruption to road users and deliver a more resilient, long-term outcome for the local community. Environmental rehabilitation formed an important component of the works, with more than 150 trees planted and site-generated mulch reused to support revegetation, stabilise disturbed areas and enhance the surrounding landscape.
-
Sector
Natural disaster recovery, Slope stabilisation, Transport
-
Client
Transport for NSW
-
Location
Mount Victoria, NSW
-
Duration
January 2025 - October 2025
-
Value
$20M
Project Scope
- Establishment of a temporary work site to enable safe construction access
- Strengthening of an existing track behind the slope for access and operations
- Clearing and trimming of vegetation
- Installation of 2,600 lm of soil nails
- Application of 900 m² of shotcrete with mock rock finish
- Installation of horizontal drainage across the slope
- Construction of 110 lm of rockfall fencing
- Installation of 226 lm of guardrail
- Replacement of road shoulder pavement
- Construction of 33 lm of concrete drainage with mock rock finish
- Site restoration including revegetation and landscaping