Hale Street East Bikeway

McIlwain delivered the Hale Street East section of Brisbane's Bicentennial Bikeway, transforming a constrained and heavily utilised corridor into a safer, higher-capacity shared path for cyclists and pedestrians along the Brisbane River.

The project involved reconstructing approximately 300 metres of bikeway between the Merivale Rail Bridge and William Jolly Bridge, creating a wider, safer shared path with improved separation between cyclists and pedestrians. Key works included an elevated riverside section supported by precast concrete girders, as well as retaining walls, cast-in-situ concrete structures, path lighting and landscaping.

Constructed within a highly constrained corridor between Coronation Drive and the Brisbane River, the project presented significant challenges including limited site access, complex geotechnical conditions, tidal influences and proximity to a heritage-listed retaining wall. Innovative construction methodologies and careful staging were employed to safely deliver the works while minimising impacts on road users and the surrounding environment.

Completed ahead of schedule and under budget, the project enhanced the capacity, safety and connectivity of one of Brisbane’s most important active transport routes.

  • Sector

    Marine, Sport and recreation

  • Client

    Brisbane City council

  • Location

    Brisbane, QLD

  • Duration

    June 2011 - December 2011

  • Value

    $6.8M

  • Achievement

    2012 Civil Contractor's Federation Earth Award - Category Three

Project Scope

  • 1500m2 of clearing and grubbing
  • Bulk excavation and removal of 1000m3 of spoil
  • 1500m of micropiling
  • Bridge construction
  • Drainage
  • Asphalt pavements and marking
  • Landscaping
  • Electrical and lighting