Skip to content

Carrara Stadium

McIlwain delivered the civil works package for the Gold Coast Stadium Upgrade at Carrara, helping transform the venue into a premier sporting facility capable of hosting major national and international events.

Undertaken within a busy construction environment, the project required close coordination with multiple contractors and careful planning to maintain progress across the site. McIlwain also undertook upgrades to the surrounding road network, including intersection improvements, bus bays, U-turn facilities and a taxi rank, all constructed to Department of Transport and Main Roads standards.

With project completion aligned to the stadium’s opening event schedule, significant resources were deployed to accelerate delivery. The successful outcome demonstrated McIlwain’s ability to remain agile, and deliver complex civil infrastructure within large-scale, time-critical environments.

  • Sector

    Sport and recreation

  • Client

    Watpac Constructions

  • Location

    Carrara, QLD

  • Duration

    November 2009 - April 2011

  • Value

    $11.3M

Project Scope

  • 50,000m3 of bulk earthworks including acid sulfate soils (ASS) treatment
  • Construction of 33,000m2 of internal asphalt pavements up to 600mm deep
  • 1,650m of stormwater drainage including GPT’s up to 8m deep
  • 2 x sewer pump stations
  • 1,100m of civil sewer installed
  • 1,500m of internal water services installed
  • 1,000t of heavy-duty asphalt pavements to DTMR standards
  • Traffic signals and street lighting