AJ Wyllie Bridge

Following significant flood damage sustained during the 2011 Queensland floods, McIlwain reconstructed the AJ Wyllie Bridge at Petrie, restoring a critical transport link and improving flood resilience for the local community.

The project involved demolishing and replacing the existing northbound bridge over the North Pine River with a higher-level structure designed to improve flood resilience and match the adjacent southbound bridge. Delivered as part of Queensland’s flood recovery program, the works restored a critical connection for the growing Moreton Bay region.

To maintain community access throughout construction, temporary pedestrian and cyclist diversions were implemented, including a signalised crossing and pedestrian bridge, while extensive utility relocations were undertaken to facilitate the works. A full-length temporary falsework bridge was also designed and constructed, providing uninterrupted access along the bridge alignment and enabling efficient demolition and reconstruction activities.

The innovative construction approach helped accelerate delivery while minimising disruption key stakeholders.

  • Sector

    Marine, Transport

  • Client

    Department of Transport and Main Roads

  • Location

    Lawnton, QLD

  • Duration

    January 2012 - December 2012

  • Value

    $15.5M

Project Scope

  • Construction of a 120m long temporary falsework bridge
  • Construction of 120m long temporary pedestrian diversion bridge featuring 900mm deep steel girders
  • Construction of 15,000m3 of road embankment
  • Installation of 1,200t of cement modified base
  • Installation of 2,500t of heavy-duty asphalt
  • 1,000m3 of reinforced S40 concrete
  • Installation of 250t of reinforcing steel
  • 18 x 1200mm diameter cast-in-place piles up to 30m deep
  • 78 prestressed concrete deck units 28m long
  • 600m of bridge safety rail and balustrades
  • Road lighting and traffic signals